Skip to main navigation.

Residential

RESIDENTIAL SERVICE

 

EFFECTIVE

DATE:

 

 

April 1, 2017

 

AVAILABILITY:

 

 

 

 

This schedule is available to members having loads of less than 100 kW of Demand, for all uses, subject to the established rules and regulations of the Cooperative. 

 

CHARACTER OF

SERVICE:

 

Single or Three Phase, 60 hertz, at available secondary voltages.

 

NET MONHLY

RATE:

 

 

                                      

 

 

 

 

 

 

Availability Charge       

                                                                                     

Single Phase                 @     $0.99/day

Three Phase                  @     $1.50/day

 

Energy Charges      

                                                                       

All kWh                          @    $0.087/kWh

    

MINIMUM CHARGE:

 

 

The minimum monthly charge shall be the applicable Service Availability charge.

 

TAXES:

 

 

 

The above rate shall be subject to all sales and franchise taxes levied or imposed by laws or ordinances as incurred by the Cooperative.

 

CONDITIONS OF SERVICE:

 

 

 

 

Unless specifically permitted by a contract, use must be limited to the member’s own premises and power supplied must not be resold.  If more than one meter is required by the member’s installation, or for the member’s convenience, bills will be independently calculated for each meter.

 

POWER FACTOR ADJUSTMENT:

 

 

 

 

Demand charges may be adjusted to correct for power factors lower than 90% when Cooperative deems necessary. Such adjustments will be made by increasing the measured demand 1.0% for each 1.0% by which the average power factor is less than 90% lagging.

 

DELIVERY POINT:

 

 

 

 

 

 

Unless otherwise specified in the service contract, the delivery point shall be the metering point where service is furnished at secondary voltage or the point of attachment of the Cooperative’s primary line to the member’s primary facilities if service is furnished at primary line voltage. The member is solely responsible for all wiring, equipment, and safe usage of electricity at and beyond the point of delivery.

 

TEMPORARY SERVICE:

 

 

 

 

 

Temporary service shall be in accordance with the rate schedule, except that the member shall pay, in addition to the specified rate and charges, construction and demolition costs associated with the service, less the value of material returned to stock. An advance deposit may be required of the full amount of the total estimated costs.

 

TERMS OF PAYMENT:

 

 

 

 

The above charges are net. Gross charges are ten percent (10%) higher. In the event payment is not made by or on the 15th day after the postmark date of the bill, the gross charges shall apply. Member will be disconnected if bill has not been paid on the disconnect date. Upon service re-connection, service fee(s) will be charged to the account.

 

   
   
   
   
   
   
   
   
   
   
   

 